Activity Duration (week) Predecessors C,E,D a) Draw AOA network diagram (grading will be done only for AOA, not AON] (12 pts) a) When will the project be available (completion of project)? (2 pts) b) What is the effect on the project if activity E takes an extra week? (3 pts)
Consider the following table: Activity Initial Node Final Node Estimated Duration A 1 1 a. Draw an AOA network diagram for the above activity list for a project. b. What is the critical path for this project? c. What is the shortest possible time it will take to complete this project? d. What are the total slacks and free slacks...
For the activities given in the table: Draw the AOA network diagram Find the critical activities Find the critical path Find the project completion time Time (days) Predecessors Activity Description Initial Paperwork A 3 Build Body B A 3 C Build Frame A 2 Finish Body 3 D E Finish Frame C Final Paperwork B,C 3 G Mount Body to...
In the following table the activities with their precedence sequence and expected time (days) are listed for a project Activity Immediate Predecessor(s) Time (days) E, F G, H The correct AOA precedence diagram is shown in Figure 1 Figure 2 Figure 3 Figure 1 Figure 2 Figure 3 In the following table the activities with their precedence sequence and expected...
Draw the AON and AOA network for a given problem. Activity Predecessor B B C DE DE F, G, H
Class Activity: Convert AON to AOA AON) (Find AOA?)
Problems 3.4.3.14 relate to Project Management Techniques • 3.4 Using the project information listed in the table below: a) Draw the AON network for the construction activity. b) Draw the AOA for the construction activity. ACTIVITY IMMEDIATE PREDECESSOR(S) DURATION (DAYS) A 4 B - 2 с 2 D A 2. E B 3 B 4 F G 2 H с...
Q1. a) Draw a project network using (AOA) method, b) and calculate (EST, EFT, LFT, LST) for each activity, c) and define the critical path. Activity Symbol A B C Predecessor Activity D E F G Duration (Weeks) Nil Nil Nil 5 9 4 B 7 AC C 8 7 D F
Here is an Activity on Arrow (AOA) network diagram for a project. The lettered A through F represents an activity, as shown in the accompanying precedence diagram. The probabilistic time for each activity is as follows Activity Time Activity Time A 4-5-6 D 4-5-6 B 2-5-6 E 2-5-6 C 3-4-5 F 3-4-6 What is the expected time and standard deviation...
W4A2: Tasks: See above to view the network diagram. Using the diagram, find: -The critical path. -How long it will take to complete the project? -How does simulation determine the probabilities of various project completion times? -What is "slack" and why is it important? -Why is activity-on-arrow (AOA) or activity-on-node (AON) of significant value to the project manager? -How is...